Risks, Issues & Decisions

Risks, Issues & Decisions

Rate risks on a project risk matrix, plan and track their mitigation, compare alternatives in weighted trade studies, test the result's sensitivity and record decisions.

How to use it →

On this page
  1. Overview
  2. Concepts
    1. The project risk scale
    2. Risk attributes
    3. Requirements at risk
    4. Burn-down
    5. Trade studies and decisions
  3. How to use it
    1. When and why
    2. Set up the risk scale
    3. Record and rate a risk
    4. Plan the mitigation
    5. Review the register
    6. Run a trade study and record the decision
    7. Worked example: the CubeSat EO-1 demo
    8. Tips and good practice
    9. Common mistakes
    10. How it connects
  4. Risk Register
    1. Page header
    2. Filter bar
    3. Columns
    4. Selection and inspector
    5. Empty states
  5. Risk Scale
  6. Risk Diagrams
  7. Risk Burn-Down
    1. Toolbar
  8. Trade Studies
    1. Trade study list
    2. Study page
    3. Decision Matrix tab
    4. Pugh Matrix tab
    5. Sensitivity tab
    6. Record Decision
    7. Exports
    8. Opportunities
  9. Issues & Actions
    1. Track an action to closure
    2. Page reference
  10. Decisions
  11. AI-assisted risks
  12. Keyboard shortcuts
  13. Messages
  14. Limits
  15. Related pages

Overview

The Risks, Issues & Decisions group answers two questions:

  • What could go wrong, and what are we doing about it?
  • Which option did we choose, and why?

It has five pages in the navigation rail:

PageWhat it shows
Risk RegisterEvery Risk in one sortable, filterable table, rated on the project risk scale, with owner, handling, residual level and mitigations.
Risk DiagramsRisk Diagrams: risks placed on the risk matrix for a root entity.
Trade StudiesWeighted decision matrices, Pugh matrices and sensitivity analysis for the alternatives of a Decision.
DecisionsThe Database filtered to the Decision class (class:Decision).
Issues & ActionsIssues, action items and nonconformances with assignee, due date and status, worked to closure.

All five pages work on ordinary model entities:

  • A risk is a Risk entity.
  • A mitigation is any Action or Task the risk is mitigated by.
  • A trade study is an Artifact labeled Trade Study.
  • A trade study's criteria are Measures labeled Criteria.
  • The choice is recorded on a Decision.

Everything you do here is traceable from the rest of the model. Every edit can be undone with a single Undo (⌘Z / Ctrl+Z).

Concepts

The project risk scale

Each project has one risk scale. It turns a risk's percentages into a level such as Low, Moderate or High. You set it with Risk Scale…. It defines:

  • Likelihood rows (1–6) and consequence columns (1–6). Each row and column has a name, a range in percent (From %, To %) and an optional definition.
  • Risk levels, listed from lowest to highest, each with a name and a color (for example Low, Moderate, High).
  • The level of each cell of the matrix.

A risk's Probability and Consequence attributes are percentages from 0 to 100. Each value falls into the row or column whose range contains it. That cell gives the risk its level.

The same scale drives the Risk Register, every Risk Diagram, the Risks panel on Home and every Risk Burn-Down. The colors and levels therefore always agree.

Two presets are built in:

PresetSizeLikelihood rowsConsequence columnsLevels
Default 5 × 55 × 5Low, Medium Low, Medium, Medium High, High (20% bins)Negligible, Minor, Moderate, Serious, Critical (20% bins)Low, Moderate, High
MIL-STD-882E (5 × 4)5 × 4Improbable (0–5), Remote (5–20), Occasional (20–50), Probable (50–80), Frequent (80–100)Negligible (0–25), Marginal (25–50), Critical (50–75), Catastrophic (75–100)Low, Medium, Serious, High

In the Default 5 × 5 preset, multiply the probability index by the consequence index (each 1–5). A cell is:

  • High when the product is 15 or more, or when the consequence is in the highest column and the probability in row 3 or above;
  • Moderate when the product is 5 or more;
  • Low otherwise.

Any edit to a preset changes the Preset box to Custom.

Exposure is Probability × Consequence / 100. It appears in exports and breaks ties when you sort by Level.

Risk attributes

Besides Name, Number and Description, a Risk has these attributes:

AttributeTypeMeaning
ProbabilityPercent (0–100)Current likelihood.
ConsequencePercent (0–100)Current severity.
Consequence DescriptionTextWhat happens if the risk occurs.
StatusChoiceOpen, Duplicate, Declined, Resolved, Mitigating, Watch.
OwnerTextPerson or team responsible for tracking and handling the risk.
Mitigation StatusChoiceAccept, Avoid, Mitigate, Transfer, Watch: how the risk is handled (LML 2.0). Shown as Handling in the register. Projects created before it have Handling Strategy with the same values instead, and keep using it.
TrendChoiceDecreasing, Increasing, New, Unchanged: whether the risk is getting worse or better since the last review (LML 2.0; projects created since, or after Schema → Add New Built-ins…).
Residual ProbabilityPercentExpected probability after the planned handling is complete.
Residual ConsequencePercentExpected consequence after the planned handling is complete.
Need-by DateDate and timeDate by which the handling must take effect.
TriggerTextEvent or indicator showing that the risk is about to occur.
Closure RationaleTextWhy the risk was closed, retired or declined.

These relationships matter for risks:

  • mitigated by: the actions or tasks that reduce the risk.
  • caused by / causes: what the risk comes from.
  • resolves.

A Risk Diagram collects the risks that its root entity causes, is caused by, mitigates or resolves.

Requirements at risk

Holarch does not add a "threatens" relationship. In LML a risk is attached to what causes it, and the requirements at stake follow from the model:

  • A risk is caused by an asset, action, connection or other element.
  • The requirements at risk are those that element satisfies or is traced from. The parts of the element (decomposed by) and the actions it performs count too, one level down.
  • If the cause is itself a requirement or statement, it is listed directly.
  • Measures and other characteristics that specify the risk are listed as well.

The list is derived, read-only and updated with every change. It appears in three places:

  • The Requirements at Risk column of the Risk Register, with the path in the tooltip.
  • The Trace section of the risk's inspector, after the relationships you edit, for example 3.1 Autonomy 72 h, via EPS → Battery (decomposed by → satisfies).
  • The Trace section of a requirement's inspector, under Risks after the relationships, highest level first.

Burn-down

A Risk Burn-Down is a chart on one Risk. It plots the risk's level over time as a step line with two series:

  • Actual: dated snapshots of Probability and Consequence, recorded as the risk is reassessed.
  • Planned: the step-down expected when each mitigation completes.

A mitigation's completion date comes from the Mitigation Plan. If none is set there, it comes from the mitigation's Start plus Duration.

Snapshots… edits the snapshot table (date, probability, consequence, note). The look of the actual line (Line colour, Point colour, Point style, Point radius) and the title, axes, legend and grid are set in the inspector's Chart section, with no Apply step (see Project Management).

Trade studies and decisions

A trade study compares the alternatives of a Decision against weighted criteria.

  • Alternatives are the entities the Decision has an alternative relationship to. They can be Assets, Actions, Artifacts, Resources, Statements or Requirements. + New creates an Asset.
  • Criteria are Measures labeled Criteria that specify the study. Each has a Weight, an Improvement Direction (higher or lower is better), Units and a Scoring Method.

Holarch scores each alternative in three steps:

  1. Each raw value becomes a score from 0 to 10, using the criterion's scoring method. A missing value counts as 0.
  2. The weights are normalized: each is divided by their total, so they sum to 1.
  3. The alternative's weighted score is the sum of its scores times the normalized weights.

Scoring methods:

MethodHow a raw value becomes a score
Direct 1-10The value is the score.
Direct 1-5The value is doubled (5 → 10).
Linear0 at the worst value, 10 at the best value, linear between, clamped outside. The worst and best values are saved as the Measure's Threshold Value and Objective Value. Leave both blank to use the range of the entered values.
ThresholdsStep scores from value:score pairs such as 100:2, 200:6, 300:10. When higher is better, a value earns the best score of every threshold it meets or exceeds. When lower is better, it earns the best score of every threshold it is at or below. Saved as Score Thresholds.

Values can carry units: 450 g in a criterion whose Units are kg is converted to 0.45.

A Decision has these attributes: Status, Justification, Assumptions, Decision Date and Decided By. Status holds the LML 2.0 states Open and Closed next to the trade-study stages (In Analysis, Decided, Deferred, Superseded) and the formal-program workflow (Draft, Submitted, Approved, Rejected, Withdrawn) in projects created since; older projects keep the values they had, and Schema → Add New Built-ins… appends the new ones. The chosen alternative is marked on its alternative relationship, in the Choice attribute.

How to use it

When and why

Risk management runs through the whole lifecycle. Start the register at the concept stage, as soon as requirements and a first architecture exist. Review it at every milestone (SRR, PDR, CDR).

The register answers:

  • Which risks threaten the mission?
  • Who owns each one, and how will we handle it?
  • Is it going down on schedule?

Run a trade study where the design branches. That is after the requirements and measures of effectiveness are known, and before the architecture is committed. A trade study answers:

  • Which alternative best meets the weighted needs?
  • Would a reasonable change in priorities change the answer?

Record the result on a Decision. Reviewers can then trace the choice back to requirements, criteria and scores.

Set up the risk scale

Set the scale before you rate many risks. Changing it later re-bins every risk. That is correct, but it can surprise reviewers who remember the old colors.

  1. Open Risks, Issues & Decisions → Risk Register.
  2. Click Risk Scale… in the page header.

    The risk scale editor opens.

  3. In Preset, choose Default 5 × 5 or MIL-STD-882E (5 × 4).

    To use your program's own matrix instead, set Likelihood rows (1–6) and Consequence columns (1–6).

  4. Under Likelihood (Probability attribute, highest first), adjust each row's Name, From %, To % and Definition.
  5. Under Consequence (Consequence attribute, lowest first), adjust each column the same way.
  6. Under Risk Levels, edit the levels. List them from lowest to highest.
    • Rename a level or pick its color.
    • Click × to remove a level.
    • Click + Add Level to add one.
  7. Under Level of Each Cell, click a cell to cycle it through the levels.
  8. Under Cell Names and Colours, give a cell a name (shown in that cell on the Risk Diagram) or its own fill colour; × goes back to the level colour.
  9. Click Apply.

    The toast Risk scale updated appears. Every risk view in the project now uses the new scale.

Press ⌘Z / Ctrl+Z to undo the change.

Record and rate a risk

  1. In the Risk Register page header, click + New Risk.
  2. In the Create Item dialog, type a Name. Optionally add a Number and a description.
  3. Click Create.

    The new risk is selected and shown in the inspector.

  4. In the inspector, set Probability and Consequence (0–100).

    The register row shows the level as soon as both are set, for example High (4×5).

  5. Set Status, Owner, Mitigation Status (or Handling Strategy in older projects), Trigger and Need-by Date.
  6. Relate the risk to what causes it with caused by, for example the subsystem.

    The risk now appears on that entity's Risk Diagram.

To draft risks with AI instead, select an entity such as a subsystem. Then choose ✦ AI ▾ → Generate Risks… (see AI-assisted risks).

Plan the mitigation

  1. Create the actions or tasks that reduce the risk, with Start and Duration. A Kanban board is a good place for them (see Project Management).
  2. In the risk's inspector, add each one to its mitigated by relationship.

    The register's Mitigations column lists them.

  3. Set Residual Probability and Residual Consequence: the rating you expect once handling is complete.

    The register shows the Residual Level next to the current one.

To plan the burn-down:

  1. Open Plan → Charts.
  2. Click + New Chart and choose Risk Burn-Down as the Chart type.
  3. In Root Risk, type the risk's name and pick it from the list.
  4. Click Create.

    The register now shows Burn-down beside the risk's name.

  5. In the burn-down, click Mitigation Plan….
  6. For each mitigation, set Completes and Level After.
  7. Click Apply.

    The planned line steps down at those dates.

To add another mitigated by entity from the Mitigation Plan dialog, click + Relate Mitigation….

Review the register

  1. Sort by Level to bring the worst risks to the top. This is the default sort, highest first.
  2. Click a level chip, for example High (2), to show only that level. Click it again to clear it.
  3. To narrow further, use Any status, Any handling and Search risks.
  4. Click Status, Owner or Handling in a row to change it in place (or press Enter or F2 on it).
  5. Reassess each risk's Probability and Consequence.
  6. Open the risk's burn-down and click Record Snapshot.

    The actual line gets a new step at today's date.

  7. For the review package, choose Export ▾ → Excel (XLSX) or CSV.

Run a trade study and record the decision

Create the study

  1. Open Risks, Issues & Decisions → Trade Studies.
  2. Click + New Trade Study.
  3. Type a Name.
  4. In Decision, choose an existing Decision, or keep New Decision and type a New Decision name.
  5. Click Create.

    The study page opens. A new Decision starts with Status In Analysis.

Add alternatives and criteria

  1. In the Alternatives bar, click + New to create an Asset, or + Existing… to pick any entity.
  2. On the Decision Matrix tab, add criteria with + Criterion or + Existing Measure….

    To have AI propose them, choose ✦ AI ▾ → Suggest Criteria from Requirements and MOEs….

  3. For each criterion, set Weight, Better (Higher or Lower) and Units.
  4. Click the criterion's Scoring button and choose the scoring method.

Score and check

  1. Type a raw value in each cell. Or click Pull Values from Model to read each alternative's Characteristics that have the criterion's name.

    The small number next to each value is its 0–10 score. The Weighted score (0-10) row and the Ranking chart update as you type.

  2. Optional: open the Pugh Matrix tab, choose the Datum and click Fill from Scores. You can also click cells to set +, 0 or −.
  3. Open the Sensitivity tab. Read the Weight Sweep for each criterion, the Tornado and the Rank Reversal Points table.

    Robust means that no change of that weight alone changes the leader.

Record the decision

  1. Click Record Decision….
  2. Choose the Selected alternative.
  3. Edit the Rationale, or click the draft button next to it to have AI draft it.
  4. Check Date and Decided by.
  5. Click Record Decision.

    The toast Decision recorded appears.

  6. To share the study, choose Export ▾ → Excel Workbook (.xlsx) or Word Summary (.docx).

Worked example: the CubeSat EO-1 demo

Create the demo project with Manage Projects → Project Files ▾ → New Demo Project.

Risk register

The demo uses the Default 5 × 5 scale and holds eight risks, RK-1 to RK-8. Sorted by Level, three are High and five are Moderate:

  • RK-1 Reaction Wheel Failure (P 45%, C 85%) is High. The ADCS Lead owns it; its handling is Mitigate and its status Mitigating. It is mitigated by KB.1 Run Reaction Wheel Life Test and KB.10 Diagnose Wheel Friction. Its residual rating (20%, 60%) is Moderate.
  • RK-3 Launch Slip (P 65%, C 70%) is High.
  • RK-7 Optical Misalignment in Thermal Cycling is Accepted, so its residual level equals its current level.
  • RK-8 Image Quality Below the Customer Need (P 65%, C 70%) is High. It is caused by RK-1, RK-5 and RK-7, combined by an OR gate: its Fault Tree computes the top probability 0.6494 from their probabilities (45%, 25% and 15%).

Try it:

  1. Click High (3).

    The register lists the three high risks.

  2. Select RK-3 and read its Trigger.

    It reads: The rideshare provider reports a manifest change or a primary payload delay.

  3. Click Burn-down beside RK-2 Battery Capacity Fade.

    The actual line has four snapshots from January to October 2026, with probability falling from 70% to 45%. The planned line steps to Moderate when KB.2 Characterize Battery Cell Fade completes on 16 October 2026. It steps to Low when KB.11 Qualify Second Battery Cell Lot completes on 29 January 2027.

  4. Open Risks, Issues & Decisions → Risk Diagrams and the EO-1 Spacecraft diagram.

    The eight risks sit on the matrix, each in its cell.

Trade study

Open Trade Studies → TR-1 Downlink Band Selection. It supports DEC-1 Select Payload Downlink Band. It compares the S-band, X-band and Ka-band transmitters on six criteria:

CriterionWeightScoring
Data Rate3Linear 8 → 60 Mbps
Mass1lower is better
Power Draw2lower is better
Ground Station Availability3Direct 1-10
Licensing Schedule2Direct 1-10
Recurring Cost2lower is better
  1. Look at the Decision Matrix.

    The weighted scores are S-band 7.24, X-band 6.13 and Ka-band 3.38. Mass, Power Draw and Data Rate were pulled from each transmitter's Characteristics.

  2. Open Sensitivity and choose Data Rate in the Weight Sweep.

    Its normalized weight is 0.231. X-band overtakes S-band at 0.328, and Ka-band leads above 0.683. Every other criterion is Robust.

  3. Open the Pugh Matrix.

    It uses S-band as datum. X-band and Ka-band are better only on Data Rate.

  4. Read the recorded decision.

    It is S-band, 18 June 2026, with a rationale that names the sensitivity to the data rate weight. Reopen would clear it and set DEC-1 back to In Analysis.

Tips and good practice

  • Write risks as condition → consequence, for example "Cells lose capacity faster than the vendor data shows". Put the effect in Consequence Description.
  • Give every risk an Owner and a Need-by Date. A risk without an owner is not managed.
  • Use the handling (Mitigation Status or Handling Strategy) honestly. Accept and Watch risks need no mitigations, but they still need a trigger.
  • Set residual values before mitigations start. The gap between current and residual level is what the mitigation plan is buying.
  • Record a burn-down snapshot at each review, not at each edit. The actual line then shows the program's assessments.
  • Set trade study weights first, from the requirements and stakeholders, before you enter values. Say so in the rationale.
  • Check the Sensitivity tab before recording. A reversal close to the current weight means the decision depends on a judgment call. The Distance pill turns amber below 0.1.
  • Use Linear with explicit worst and best values for measured criteria. If you leave them blank, scores scale to the entered values, so adding an alternative can change every score.

Common mistakes

  • A risk shows "—" as its level. Probability or Consequence is empty. Set both. The register lists such risks under Not rated.
  • A risk is missing from a Risk Diagram. The diagram shows only risks related to its root (causes, caused by, mitigates, resolves), or with Include set to All levels also those of the root's decomposition, minus hidden labels. Relate the risk to the root, or set Include to All levels.
  • Record Snapshot fails with The risk has no Probability or Consequence. Set both, then record a snapshot. Set both values first.
  • Record Decision… is disabled. The study has no Decision or no alternatives. Relate the study to a Decision with enables, then add alternatives.
  • Pull Values from Model finds nothing. The Characteristic must be related to the alternative and have exactly the criterion's name. Case does not matter.

How it connects

  • Requirements and measures feed the trade study criteria. Suggest Criteria from Requirements and MOEs… reads requirements and Measures labeled MOE, MOP, KPP or TPM. Trace the Decision from the requirement it answers (traced from), as the demo does for DEC-1.
  • Architecture: alternatives are usually Assets, and the chosen one becomes part of the design. Their Characteristics (mass, power) come from the budgets.
  • Plan: mitigations are Tasks on a Kanban board or Gantt chart, and the burn-down uses their dates. See Project Management.
  • Verification: failed tests often raise or confirm risks. RK-1's trigger is a second pointing test failure.
  • Home and the rail: the Risks, Issues & Decisions badge and the Home card High risks count risks at the highest level. The Risks panel on Home shows the register as a heat map on the project risk scale.
  • Frameworks: UAF Rk-Pm views open a Risk Diagram or a risk burn-down. See Frameworks.

Risk Register

Risks, Issues & Decisions → Risk Register lists every Risk in the project.

ControlAction
Risk Scale…Opens the risk scale editor (see Risk Scale).
Export ▾Excel (XLSX) or CSV of the rows currently shown.
+ OpportunityAsks for a name and creates a Risk whose Kind is Opportunity, numbered OPP-1, OPP-2, ….
+ New RiskCreates a Risk (or a subclass) and selects it.

Filter bar

  • Level chips, one per risk level from highest to lowest, each with its count, plus Not rated (n) when some risks have no level. Click to filter; click again to clear.
  • The count, for example 7 risks. Child risks that only hold old burn-down points are not listed; the count then adds n burn-down review points not listed.
  • Any status and Any handling filter by Status and handling.
  • Threats and opportunities shows threats or opportunities only. It appears once the project has an opportunity.
  • Search risks matches number, name, owner, trigger and description.

Columns

ColumnContent
IDNumber.
RiskName (link to the Item View), plus Burn-down when the risk has a burn-down chart.
KindOpportunity, or Threat for other risks. Shown when a risk has a Kind.
StatusPill; click it to choose another.
OwnerText; click it to change it.
HandlingText; click it to choose another (Mitigation Status, or Handling Strategy in older projects).
P %, C %Probability and Consequence.
LevelLevel chip with its matrix cell, for example High (4×5). Point at it for the row and column the percentages fall into.
Residual P %, Residual C %, Residual LevelResidual values and level.
Need-byDate.
MitigationsLinks to the first two mitigated by entities, one per line (a long name ends in … ; point at it for the full name), and +N for the rest (point at it to list them), or none.
Requirements at RiskThe first three requirements at risk as links, then +n more, or none. Point at it for each requirement with its path (see Requirements at risk).
TriggerText, truncated; point at it for the full text.

ID, Risk, Status, Owner, Handling, P %, C %, Level and Mitigations always show. The other columns are hidden when no risk has a value in them. Exports always include every column plus Exposure (P×C/100), Closure Rationale and Labels. Files are named Risk_Register.xlsx and Risk_Register.csv.

Click a column header to sort; click again to reverse. Level and percentage columns sort highest first.

Selection and inspector

Click a row (or focus it and press Enter or Space) to show the risk in the inspector, where every attribute, relationship and comment can be edited. ↑ and ↓ move between rows. Esc clears the selection.

Empty states

  • This project has no risks. — Use + New Risk, or add risks on a Risk Diagram.
  • No risk matches the filters. — Clear a filter to show every risk.

Risk Scale

The Risk Scale… dialog sets the project risk scale. It opens from the Risk Register, a Risk Diagram (the toolbar, Arrange ▾ and the link in a selected cell's inspector) and a Risk Burn-Down.

FieldMeaning
PresetCustom, Default 5 × 5, MIL-STD-882E (5 × 4). Choosing a preset replaces the whole scale in the dialog.
Likelihood rows (1–6), Consequence columns (1–6)Matrix size. Changing the size resets the names and ranges to evenly spaced defaults and keeps your levels.
Likelihood (Probability attribute, highest first)One row per likelihood: #, Name, From %, To %, Definition.
Consequence (Consequence attribute, lowest first)Same for consequence.
Risk LevelsName and color of each level. × removes a level: its cells move to the next lower level, or to the next higher one when you remove the lowest. + Add Level adds one. At least two levels remain.
Level of Each CellClick a cell to cycle its level.
Cell Names and ColoursPer cell: a name (placeholder: the cell's level) and a custom fill colour with × to use the level colour. Names and colours are part of the scale; names and colours set per matrix size by earlier versions are read until the scale is next applied. Changing the size or the preset clears them.

Apply saves the scale as one undo step. Cancel discards changes.

A value exactly on a boundary belongs to the upper range (20% is in the 20–40 row), except 100%, which is in the top range. Values outside every range go to the first or last row or column.

Risk Diagrams

Risks, Issues & Decisions → Risk Diagrams lists the Risk Diagrams of the project. Open one, or create one with + New Diagram: choose Risk Diagram and type the root entity in Root.

The diagram draws the project risk matrix with each related risk in its cell and a table of the risks below it.

  • Toolbar:
    • Include: Direct risks (the risks of the root itself) or All levels (also the risks of every entity in the root's decomposition, the default). A diagram saved with Level 1 opens as Direct risks.
    • + New Risk: a risk at 50% probability and 50% consequence.
    • Relate Existing Risk…, ✦ Generate Risks and Risk Scale….
    • Filter by Label ▾: risks with a selected label are hidden. The button then reads Labels (n hidden) ▾.
    • Risk Register.
  • Cells: click a cell to select it. The inspector shows it as Cell L4 × C3 · High, with the cell's likelihood and consequence and Risks (n) as rows; click a row to show that risk. It offers + New Risk Here, a risk named New Risk with the cell's midpoint percentages, and ✦ Generate Risks… for that cell. Cell names and colours are set in Risk Scale….
  • Arrange ▾: Risk Scale… and Show risk names in cells / Show risk numbers in cells.
  • With a Risk as root, the diagram shows that risk, its decomposition and the risks related to them.

The diagram editor itself (zoom, annotations, export) is described in the diagram reference; see Risk Diagram.

Risk Burn-Down

A Risk Burn-Down is a chart in Plan → Charts whose root is a Risk. It opens from Burn-down in the register or from the chart gallery.

Toolbar

ControlAction
Snapshots…Opens Burn-Down Snapshots: a table of Date, Probability (%), Consequence (%), Level, Note and Remove, with + Add Snapshot (copies the last row's values) and + Add Current Values (the risk's current Probability and Consequence).
Record SnapshotAdds a snapshot with the risk's current Probability and Consequence at the current time. Toast: Snapshot recorded.
Mitigation Plan…Opens Mitigation Plan: each mitigated by entity with Completes (date) and Level After; + Relate Mitigation… adds one.
Risk Scale…The project risk scale.

The chart's look is set in the inspector's Chart section: title, axes, legend, grid and the Actual line (Line colour, Point colour, Point style, Point radius). Each change applies at once and can be undone with a single Undo.

The chart editor's common controls apply: ‹ All Charts, ▲ Parent, Open ▾ and Export… (Chart (PNG) with Transparent background, Chart (SVG), Chart (Word), Chart (HTML), Data (CSV)). The CSV has the columns Series, Date, Probability, Consequence, Exposure, Level and Note, with one row per actual snapshot and per planned step.

Below the chart: Current level: …, Residual (target) level: …, the snapshot count, and how many snapshots are not plotted because they lack a probability or consequence. Point at a point for its date, level, percentages, exposure and note.

Older projects recorded burn-downs as child risks that each hold one dated point. If the risk still has such child risks, a banner offers Convert…. In the Convert Snapshot Risks dialog, click Convert. The points move into snapshots and those child risks are deleted, and a single Undo takes it all back.

Trade Studies

Trade study list

Risks, Issues & Decisions → Trade Studies lists every study with Trade Study, Decision, Alternatives, Criteria, Leader (0-10) and Status (the Decision's status, or Selected: … once recorded). + New Trade Study is in the page header.

You can also start a study from a Decision: Open in ▾ on the Decision lists Trade Study: <name> for each existing study, or New Trade Study… when it has none. Open in ▾ on a study offers Open Trade Study.

Study page

The header shows the editable study name, the Decision it supports (for DEC-1 …) with its status pill, or No Decision. When a decision is recorded, a card shows Decided: <alternative>, the date, the decider, the rationale and Reopen.

Page header: All Studies, Export ▾ (Excel Workbook (.xlsx), Word Summary (.docx)) and Record Decision…. ✦ AI ▾ (in the top bar) adds Suggest Criteria from Requirements and MOEs… and Draft Decision Rationale….

Alternatives bar: a colored chip per alternative (the color is used in every chart), × to remove it from the Decision (the entity is kept), + New and + Existing….

Decision Matrix tab

ColumnContent
CriterionEditable name.
WeightRaw weight (any non-negative number).
Norm.Normalized weight in percent.
BetterHigher or Lower.
UnitsUnits of the raw values.
ScoringButton with the method summary, for example Linear 8 → 60 or Thresholds (3); opens Scoring Method · <criterion>.
One column per alternativeRaw value input and its 0–10 score.
×Removes the criterion from the study (the Measure is kept).

The footer row Weighted score (0-10) shows each alternative's total and rank (#1, #2, …). Card buttons: + Criterion, + Existing Measure…, Pull Values from Model. The Ranking card is a bar chart of the weighted scores, leader first.

Scoring Method dialog: Method (Direct 1-10, Direct 1-5, Linear, Thresholds). Linear shows Worst value: score 0 and Best value: score 10. Thresholds shows Thresholds (value:score, score 0-10). Save applies.

Pugh Matrix tab

A Pugh matrix compares each alternative with a reference alternative, the datum.

Choose the Datum; its column shows D. Click a cell to cycle 0, +, − (same, better, worse than the datum). Footer rows: Σ +, Σ −, Σ 0, Net and Weighted net. Weighted net uses the normalized weights, and the best positive weighted net is bold. Fill from Scores sets every cell by comparing each alternative's score with the datum's, criterion by criterion. Needs at least two alternatives and one criterion.

Sensitivity tab

  • Weight Sweep: choose a criterion. The chart shows each alternative's weighted score as that criterion's normalized weight goes from 0 to 1, with the other weights keeping their ratios. Shaded bands show the leader at each weight. A vertical line marks the current weight (now 0.231), and dots mark rank reversals. The sentence below names the nearest reversal, or No rank reversal: … leads at every weight of ….
  • Tornado: choose Weight change ±10%, ±25%, ±50% (default) or ±100%. Each pair of bars shows the leader's margin over the next alternative with that weight lowered (upper bar) and raised (lower bar). Bars that cross zero mark a leader change. Rows are sorted by the size of the effect.
  • Rank Reversal Points: per criterion, Current weight, Reversal at weight → new leader and Distance (how far the weight must move; Robust when it never reverses).

Needs at least two alternatives and one criterion.

Record Decision

Record Decision · <Decision> offers:

  • Selected alternative: radio buttons in rank order with each score. The leader (or the earlier choice) is preselected.
  • Rationale (saved as the Decision's Justification): prefilled with the Decision's current Justification. If it has none, you get an automatic summary of the scores and rank reversals; it follows your alternative choice until you edit it. The button next to the label drafts it with AI.
  • Date and Decided by (your name).

Record Decision saves, as one undo step:

  • the Choice on the selected alternative's relationship;
  • the Decision's Justification, Decision Date and Decided By;
  • the Decision's Status, set to Decided.

Reopen clears the choice and sets the status back to In Analysis.

Exports

  • Excel Workbook (.xlsx): sheets Decision Matrix (criteria, weights, normalized weights, direction, units, scoring, raw values and scores), Results (rank, alternative, weighted score, missing values, selected), Pugh and Sensitivity (reversals, then the tornado table).
  • Word Summary (.docx): title, decision, description, alternatives, criteria, decision matrix (Cells show the raw value and, in parentheses, its score from 0 to 10.), ranking, Pugh matrix with datum, sensitivity and tornado tables, and the recorded decision with its rationale.

Files are named after the study.

Opportunities

An opportunity is an uncertain event that would help the project, such as reusing a flight spare. Record it to plan how to make it happen.

  • It is a Risk whose Kind attribute is Opportunity (risks without a Kind are threats).
  • Rate it on the same scale. Its consequence rates the size of the benefit.
  • The Kind column shows Opportunity; threats show Threat.

Issues & Actions

Use Risks, Issues & Decisions → Issues & Actions to track problems and the work that closes them. Every project has it; no switch is needed. The address is issues (also actions).

Each row is an Issue entity. Its Kind attribute says what it is:

KindUse it forNumber
IssueA problem that needs a decision or work.ISS-1
ActionAn action item with an assignee and a due date.AI-1
NonconformanceA product that does not meet a requirement, from a failed test. See Formal Program.NC-1
RIDA review comment. Listed only under the RIDs filter; see Formal Program.RID-1

Track an action to closure

  1. Click + New ▾, then Action….
  2. Enter the Title, Assignee, Due date, Priority and Description, then click Create. An action can also name the item it Resolves (Choose…). You see the action at the top of the Open list, numbered AI-1.
  3. Change Status in the row as work progresses.
  4. When it is done, set Status to Closed. The Close dialog asks for the resolution. Click Close Item. The Closed Date is recorded with it, and a single Undo takes back both.

An issue or nonconformance cannot be closed while an action that resolves it is open: Close… is unavailable and choosing Closed shows <item> cannot be closed yet: close its actions first. Close the actions first.

To raise an action for an issue, open the issue's row ⋯ and click New Action for This…. The action resolves the issue, and its Source column names the issue.

Page reference

PartContent
+ New ▾Issue… and Action…: title, assignee, due date, priority, description, and for an action the item it resolves. A single Undo takes each one back.
Export ▾Excel (XLSX) or CSV of the rows shown, with Closed, Resolution and Description.
FiltersOpen, All, Issues, Actions, Nonconformances, RIDs and Overdue, each with its count. Search issues and actions matches number, name and assignee.
ColumnsID, Title, Kind, Status, Priority (Severity for nonconformances and RIDs), Assignee, Due, Source and Age (days open). Status, Assignee and Due read as text: click one to change it in place.
Row ⋯New Action for This…, Close… (unavailable while an action that resolves the item is open) or Reopen, Open in Item View.

An open item past its due date shows Overdue. Reopening a closed item clears its Closed Date. Click a row to see the item in the inspector; Esc deselects. The command palette has New Issue and New Action.

Decisions

Risks, Issues & Decisions → Decisions opens the Database with the query class:Decision. Each Decision shows its status, date and decider. Open one to edit its Justification and Assumptions, see its alternatives (with the Choice marked) and the study that enables it. See Database.

AI-assisted risks

AI can draft risks for an entity. Start it from any of these:

  • ✦ AI ▾ → Generate Risks… in the top bar, on an entity or a Risk Diagram;
  • ✦ Generate Risks on the Risk Diagram toolbar;
  • Generate Risks with AI… in ⌘K / Ctrl+K.

It works in two steps, and you preview both:

  1. Choose up to 3 Risks: six candidate risk names for the entity. Tick up to three, then click Next: Details. If you tick more, Choose 3 risks or fewer. appears.
  2. Review Risks: each risk with an editable number, name, category (one of the project's risk categories, or No category), Description, Consequence Description, Consequence % and Probability %. Untick any you do not want and click Add Selected Risks.

The risks are created with Status Open, related to the entity and labeled with the category, and a single Undo takes it all back. The toast reads Created n risks.

The category list is the project's own risk categories: the labels its schema gives the Risk class (Cost, Other, Schedule and Technical by default), including any you add in Schema. A suggested category the project does not have is mapped to the closest one or left unset with a note in the preview; no category is created.

On a Risk Diagram, ✦ Generate Risks works in one step instead: you choose the number of risks (1–10, default 5) and review them in one preview with the project's risk categories and numbers that follow the target's children. See Risk Diagram.

Candidates that look like they carry untrusted content, such as a web address, start unticked. If the provider returns nothing, you see <provider> did not suggest any risks.

Trade studies have two AI tools, both previewed:

  • Suggest Criteria from Requirements and MOEs… proposes 4–8 criteria from the project's requirements and its Measures labeled MOE, MOP, KPP or TPM. The Suggested Criteria dialog lists Criterion, Weight, Better, Units, Scoring and Source. Tick the ones to keep and click Add Selected (Added n criteria).
  • Draft Decision Rationale… opens Record Decision and drafts a 3–6 sentence rationale into the Rationale box (Draft inserted. Review it before you record.). Nothing is saved until you click Record Decision.

See AI for keys, providers and what is sent.

Keyboard shortcuts

KeysWhereAction
Enter or SpaceRisk Register rowSelect the risk and show it in the inspector.
↑ / ↓Risk Register rowMove to the previous or next row.
EscRisk RegisterClear the selection.
⌘Z / Ctrl+Z / ⇧⌘Z / Ctrl+Shift+ZAnywhereUndo / redo the last edit (each matrix change, recorded decision or AI apply is one step).
⌘K / Ctrl+KAnywhereCommand palette, including Generate Risks with AI….

Messages

MessageMeaning and fix
Risk scale updatedThe scale was applied.
The likelihood range of “…” is invalid. Enter From and To between 0 and 100, with From below To. (or consequence range)A row or column has an empty, out-of-range or reversed range. Fix it and click Apply again.
A risk level has no name. Name every level.Give each level a name.
The risk has no Probability or Consequence. Set both, then record a snapshot.Rate the risk before recording a burn-down snapshot.
Snapshot recordedToday's rating was added to the burn-down.
A snapshot has no date. Enter a date for every row.Fill every Date in Burn-Down Snapshots.
No snapshots yet. Use Record Snapshot or Snapshots… to add points.Empty burn-down.
No mitigations yet. Relate the actions that reduce this risk.Mitigation Plan with no mitigated by entities.
Converted n snapshots (⌘Z / Ctrl+Z to undo)Older child-risk points were converted.
Decision recordedThe choice, rationale, date, decider and status were saved.
Pulled n values from the modelValues were read from same-named Characteristics.
No matching Characteristics found. Give a Characteristic of the alternative the same name as the criterion.Pull Values from Model found nothing.
No thresholds found. Enter value:score pairs separated by commas.The Thresholds text has no valid pairs.
The AI returned no criteria. Try again, or add criteria in the matrix.Criteria suggestion came back empty.
This study enables no Decision. Relate it to a Decision with enables to add alternatives.The study is not linked to a Decision.
A Pugh matrix needs at least two alternatives and one criterion. / Sensitivity analysis needs at least two alternatives and one criterion.Add alternatives or criteria.
This project has no trade studies.Use + New Trade Study.
⚠ The draft contains a web address. Check it before you record.The AI draft includes a URL; verify it.

Limits

  • Risk matrix: 1–6 likelihood rows and 1–6 consequence columns; at least two levels.
  • Probability, Consequence and their residual values: 0–100.
  • Generate Risks: six candidates, up to three detailed per run.
  • Suggest Criteria: reads up to 80 requirements and 40 measures; proposes up to 16 criteria.
  • Pugh matrix and sensitivity: at least two alternatives and one criterion.
  • Tornado weight change: ±10%, ±25%, ±50% or ±100%.
  • Weights below zero count as zero; if every weight is zero, all criteria weigh the same.