Budgets & TPMs
Roll mass, power, cost or any quantity up the system structure with part counts, contingency, allocations and margins, and track technical performance measures against a planned profile.
On this page
Overview
Architecture → Budgets & TPMs checks whether the design still fits its resource limits. It has two tabs:
- Budget adds up a resource over an asset tree: mass, power, cost, data rate or any numeric attribute. Each line shows its estimate, contingency, allocation and margin. You see at once which subsystem is over its share.
- TPMs tracks technical performance measures (TPMs). A TPM is a Measure with a threshold, an objective and a planned value per milestone. Its estimates are charted over time, with a status of On track, At risk or Breach.
Both tabs read values with their units (12 kg, 3.5 W, $1.2M) and convert them. Subsystems can therefore report in different units.
Concepts
Current best estimate, contingency and margin
A budget line starts from one item's value and ends with the margin left against its allocation.
| Term | Meaning |
|---|---|
| Unit Value | One item's own value, e.g. one reaction wheel's mass. |
| Count | How many of the item its parent holds. |
| CBE (current best estimate) | Unit Value × Count for a leaf; the sum of its parts for a parent. |
| Basis | How the value was obtained: Estimated, Calculated or Measured. |
| Contingency | A reserve for growth: CBE × the basis's contingency %. |
| CBE + Cont. | The value you plan against. |
| Allocation | The share of the resource the line may use (for all its instances). |
| Margin | Allocation − (CBE + contingency). Margin % = Margin ÷ Allocation. |
| Required margin | The margin % below which a line is flagged ▲ Low. |
Default contingency by basis:
- Estimated: 15 %
- Calculated: 10 %
- Measured: 3 %
The default required margin is 10 %. You set both per quantity.
Technical performance measures
A TPM is a Measure with the TPM label. It uses these attributes:
| Attribute | Use |
|---|---|
| Current Estimate | The latest estimate or measurement with units, e.g. 10.4 kg. Every change is recorded in the history. When empty, Value is used. |
| Threshold Value | The worst acceptable value. Beyond it the TPM is in Breach. |
| Objective Value | The value you aim for. |
| Improvement Direction | Positive (higher is better, the default) or Negative (lower is better). With N/A, lower is better when the objective is below the threshold. |
| Tolerance | Percent the estimate may fall behind the plan before the TPM is At risk. |
| Units | The unit of a plain number. |
A requirement with a Threshold Value is tracked the same way, with its Value as the current estimate (see Budget against a requirement).
The planned profile is a list of milestones, each with a date and a planned value. Holarch interpolates the planned value for today linearly between milestones. Before the first and after the last milestone, the plan is flat.
The status is decided in this order:
| Status | Rule |
|---|---|
| ✕ Breach | The current estimate is worse than the threshold. |
| ▲ At risk | The estimate is worse than today's planned value by more than the tolerance. |
| ✓ On track | Otherwise. |
| No data | No current estimate. |
How to use it
When and why
Start a resource budget at concept definition, as soon as there is a top-level allocation: a launch mass, a power envelope or a cost cap. Refresh it at every design review, as estimates become calculations and then measurements. The budget answers: does the design still fit, and where is the margin?
TPMs follow the few parameters that decide mission success, such as mass, power margin, data rate or range. Track them from the requirements review to acceptance. They answer: are we converging on the requirement on schedule?
Pick as TPMs the parameters whose breach would force a redesign. Derive their thresholds from requirements.
Set up a budget
- Open Architecture → Budgets & TPMs.
- Click the Budget tab.
- Click Select Root Asset… and pick the system, e.g. the spacecraft.
The tree lists the root and every part below it.
- In Quantity, choose Mass, Power, Cost or Data Rate. You can also type any attribute or Characteristic name; the list offers every name already used on assets.
- In Unit, type the display unit, e.g.
kg. Leave it empty to use the unit of the largest value. - Set Required margin.
- Set the three Contingency by basis percentages.
Lines without a value show an empty Unit Value field.
Enter values and allocations
- In Unit Value, type each leaf's value with its unit:
2.4 kg,850 g.If the item has no attribute or Characteristic of that name yet, Holarch creates and links a Characteristic (Creates a "Mass" Characteristic).
- In Basis, choose Estimated, Calculated or Measured.
The Cont. column updates.
- For a part used more than once without a multiplicity, type the Count.
- In Allocation, type the root's allocation, e.g.
12 kg. - Type an Allocation on each other line that has one.
- Read the summary tiles and the Margin columns.
- ✓ means the margin is fine.
- ▲ Low means the margin is below the required margin.
- ✕ Over means the line exceeds its allocation.
- A ⚠ after a name marks a problem on that line. Point at it to read the problem.
- To share the budget, click Export XLSX in the page header.
You get a workbook with status colours.
Budget against a requirement
A requirement such as The rover mass shall not exceed 12 kg (objective 10 kg) can set the allocation itself.
- Open the requirement in the Database or the inspector.
- Set Budget Quantity to the budget's quantity, e.g.
Mass. - Set Threshold Value to
12 kgand Objective Value to10 kg.Plain numbers take the requirement's Units.
- Link the requirement to the asset that meets it with satisfied by.
- Open the Budget tab with that quantity.
The asset's line uses the threshold as its Allocation when none is typed. Point at the allocation to see which requirement it comes from. The summary shows Allocation (requirement) and Objective with met or not met.
- To use a different allocation, type it in Allocation. Clear it to go back to the requirement's threshold.
- When several requirements on the same quantity apply to one item, the lowest threshold is used.
- A threshold is an upper limit. A requirement whose objective is above its threshold is a minimum and does not set an allocation.
- Requirements with a Threshold Value are also listed on the TPMs tab. Their current estimate is their Value; when it is empty, it is the budget total (CBE + contingency) of the items that satisfy them. A change of Value is recorded in the history like a Current Estimate.
In a SysML v2 project the threshold and objective are in the model (Threshold and objective):
- Write the requirement's threshold as a
requireconstraint, for examplerequire constraint { car.curbMass <= limit }, and its objective as@Objective { value = 1600 [kg]; }. - Link it with
satisfy carSpec by fleet.sedan;. - Open the Budget tab with a quantity whose name ends the constrained attribute's name:
MassorCurb Massforcar.curbMass.The part's line uses the threshold as its Allocation when none is typed.
- Upper limits (
<=) set allocations; minimums (>=) do not. - A requirement nested in a satisfied requirement (
carSpecholdssedanMass) applies to the same part. - On the TPMs tab, the current estimate is the value the satisfying part gives the constrained attribute (
attribute redefines curbMass = 1580 [kg];), else that part's budget total (CBE + contingency). It comes from the model, so the field cannot be edited.
Track a TPM
- Create a Measure, in the Database or from the Add panel of a Radar diagram.
- Link the Measure to the asset it describes with specified by.
- Add the TPM label to the Measure.
- Set its Threshold Value, Objective Value, Improvement Direction and Tolerance.
- Open the TPMs tab and click the Measure's row.
Its detail card opens below the list.
- Click + Milestone.
- Fill in Milestone (e.g.
PDR), Date and Planned value (12 kg), then click Add. - Repeat the last two steps for each review.
- As the design matures, type the new Current Estimate.
Each change adds an Automatic point to Estimate History. Changes within one minute replace the previous automatic point.
- At a moment you choose, such as a review, click Take Snapshot.
The current value is recorded as a Snapshot point.
- Type a Note next to the snapshot.
- Read the status beside the name and the chart.
The chart shows the current estimate, planned profile, threshold, objective, breach region and today.
Worked example: the CubeSat EO-1 demo
Create the demo with Manage Projects → Project Files ▾ → New Demo Project. Then open Architecture → Budgets & TPMs.
- Look at the Budget tab.
It opens on 1 EO-1 Spacecraft, quantity Mass, unit
kg, required margin 10 %. The tiles read:- Current best estimate 9.63 kg
- Contingency 0.7656 kg (7.95%)
- CBE + contingency 10.3956 kg
- Allocation 12 kg
- Margin 1.6044 kg (13.4%)
- Status ✓ Margin met
- Find 1.2.1 Reaction Wheel Assembly.
Count shows ×4, from multiplicity 4 on the BDD. Each wheel is 0.13 kg, so the CBE is 0.52 kg, Measured, with 3 % contingency. 1.3.1 Solar Arrays shows ×2.
- Find 1.1 Payload Camera.
It is flagged ▲ Low. 2.4 kg Calculated + 10 % = 2.64 kg, against a 2.75 kg allocation. That leaves 0.11 kg, a 4 % margin, under the 10 % required.
- Change Quantity to Power Draw.
The root reads CBE 23 W, CBE + contingency 25 W, allocation 28 W, margin 3 W (10.7%). Solar Arrays and Battery Pack draw no power and have no value.
- Open the TPMs tab.
Three TPMs are listed:
- TPM-1 Spacecraft Mass: 10.4 kg, threshold 12 kg, objective 10 kg, lower is better: ✓ On track.
- TPM-2 Orbit-Average Power Margin: 10.7 %, threshold 10 %, objective 20 %: ▲ At risk, 10.7% is below the planned 19.71% for today. The history shows the drop at PDR (PDR: payload heater load added).
- TPM-3 Payload Downlink Rate: 10 Mbps against a threshold of 8 Mbps: ✓ On track.
- Select TPM-2 and type
9.5 %as Current Estimate.The status turns ✕ Breach (9.5% is below the threshold 10%.). A point is added to the history. The TPM breaches card on Home and the Architecture badge count it.
- Press ⌘Z / Ctrl+Z to undo.
The camera in step 3 has three ways out:
- Measure the camera. Measured cuts contingency to 3 %, giving 2.472 kg and a 10.1 % margin.
- Find mass elsewhere and raise the camera's allocation.
- Accept the risk.
Tips and good practice
- Budget leaves, allocate branches. Put Unit Values on the lowest items you can estimate, and allocations on subsystems. The parents add up by themselves.
- Move the basis forward. Go from Estimated to Calculated to Measured as the design matures. The contingency falls with each step; this is how real margin is recovered.
- Keep the basis honest. A catalogue mass is Calculated until the flight unit is weighed.
- Keep child allocations within the parent's. If they add up to more, the parent shows ⚠ Child allocations total …, more than this allocation.
- Link each TPM to its requirement with specifies, and set the threshold from that requirement.
- Take a snapshot at each review, so the history shows the value the review saw.
Common mistakes
- A value in the wrong kind of unit, such as
6 Win the mass budget. The line shows ⚠ power value in a mass budget. Fix the units. and is left out of the sum. Fix the unit. - A plain number, such as
12, in a budget with no unit set. It is read in the unit of the other values. Type the unit to be sure. - The wrong Improvement Direction. It is Positive by default, but lower is better for mass, cost and latency. Set Negative, or the status reads On track while the value grows.
How it connects to other features
Budgets and TPMs are fed by:
- the asset decomposition and its multiplicities (Asset and Block Definition diagrams);
- Characteristics on assets, which Parametric diagrams also use;
- Cost entities, for cost budgets;
- interface data rates (see Interfaces).
They feed:
- Home: the TPM breaches card and a next action Close 1 TPM breach: …, plus the Architecture badge.
- Model checks: check Measure.1 compares a Measure's Projected Value, or Value, with its Threshold Value.
- Radar diagram: it plots the Value, Projected, Threshold and Objective of Measures.
- Trade studies: their criteria often use the same quantities (Risks, Issues & Decisions).
- Verification: a Measure can carry a simulation result for a requirement (Verification).
A Parametric diagram binds Characteristics to constraint equations such as P_oa >= P_load * (1 + M_req). It solves them with the same units and writes the solved values to the Characteristics. A budget or TPM that reads them then updates. See SysML diagrams and Parametric Diagram.
How values are read
This section explains where each number in the budget comes from. Read it when a line shows a value you did not expect.
Where values come from
For the chosen quantity name (for example Mass), Holarch reads each item's own value from the first of these that exists:
- An attribute of the item with that name.
- A Characteristic with that name that specifies the item, using its Value and Units.
- For Cost only: the Cost entities the item incurs, summed from their Amount and Units.
A plain number without units takes the budget's unit.
When no allocation is typed in the budget, the allocation is read the same way. Holarch looks for an attribute or Characteristic named <quantity> Allocation, e.g. Mass Allocation.
Count
Holarch takes an item's count from the first of these that exists:
- The Multiplicity on its decomposition, set on the composition line of a Block Definition Diagram. A range such as
2..4counts its upper bound. - The item's Quantity attribute.
- Otherwise, 1.
Children ▾ → Roll Up… on the Item View (More ▾ → Rollup… in the Database) and Roll Up in the Hierarchy Diagram's Diagram Settings both sum the children's values. To keep such a total up to date, click Keep Live in that dialog (offered when the class has a Computed attribute). You can also build the formula of a Computed attribute with + Children's Values. It can weigh each child by its Multiplicity or Quantity (× part count).
Roll-up
- A leaf contributes Unit Value × Count.
- A parent with at least one valued part shows the sum of its parts, times its own count. Its own value is ignored, and a ⚠ note says so.
- A parent's contingency % is the weighted result of its parts.
Units and quantities
Values are quantities: a number with a unit. Holarch converts between units of the same kind. It refuses to add different kinds: a power value in a mass budget is flagged and left out. Supported units include:
| Kind | Units |
|---|---|
| Mass | g (with SI prefixes, e.g. kg, mg), t/tonne, lb/lbm/lbs, oz, slug, ton |
| Length | m (SI prefixes), in, ft, yd, mi, nmi, mil, au, ly |
| Time | s (SI prefixes), min, h/hr, d, wk, mo, yr |
| Power and energy | W, J, Wh, cal, eV (SI prefixes, e.g. kW, kWh), hp, BTU |
| Force and pressure | N, lbf, kgf, dyn; Pa, bar, atm, psi, ksi, torr, mmHg, inHg |
| Electrical | A, V, Ω/ohm, Ah (SI prefixes) |
| Frequency | Hz (SI prefixes), rpm |
| Data and data rate | bit/b, B (SI and binary prefixes: kB = 1000 B, KiB = 1024 B), KB; bps, Bps, Kbps (SI prefixes, e.g. Mbps) |
| Angle | rad, deg/°, arcmin, arcsec, rev |
| Temperature | K, °C, °F, °R; differences Δ°C, Δ°F |
| Area and volume | ha, acre, m^2; L (SI prefixes), gal, qt, pt, floz, cc, m^3 |
| Speed | mph, kph, kn, fps, m/s; acceleration gn, m/s^2 |
| Ratio and count | %, ppm, ppb, ea/each/pcs/count |
| Cost (US dollars) | $/USD, $K, $M, $B (also $1.2M) |
More rules:
- Write compound units with
/,*,^or per:ft/min,W/m^2,kg*m/s^2,N·m,sq ft. - Unit names work too: kilograms, watts.
- A word that is not a unit (
4 motors) becomes its own kind. It only adds to values with the same word. - Other currencies are kept as their own unit and are not converted.
Budget tab
The Budget tab has a row of controls, summary tiles for the root, and the budget table.
Controls
| Control | Use |
|---|---|
| Root asset | Select Root Asset… (or the current root) opens the asset picker. Ports are excluded. In a SysML v2 project the control is Root part, with Select Root Part… for a part or part definition. |
| Quantity | Name to roll up. The list offers Mass, Power, Cost, Data Rate, every numeric, text, percent or duration Asset attribute, and every Characteristic name used on an asset with a numeric value. |
| Unit | Display unit (placeholder auto), e.g. kg, lb, W, $K, Mbps. |
| Required margin | Percent, 0–100. |
| Contingency by basis | Estimated, Calculated, Measured, each 0–500 %. |
Unit, required margin and contingency are saved per quantity. The mass and power budgets therefore keep their own settings.
Changes to these settings can be undone. Choosing the root or the quantity is not an edit and is not on the undo stack.
Summary tiles
Current best estimate, Contingency (with %), CBE + contingency, Allocation, Margin (with %) and Status for the root:
| Status | Meaning |
|---|---|
| ✓ Margin met | Margin at or above the required margin. |
| ▲ Margin below N% | Positive margin, below the required margin. |
| ✕ Over allocation | CBE + contingency exceeds the allocation. |
| Set an allocation on the root | Values exist but the root has no allocation. |
| No values yet | No line has a value. |
Table
| Column | Content |
|---|---|
| Item | Number and name (link to the Item View), ▾/▸ to collapse, ⚠ with the line's problems on hover. |
| Count | ×N from a multiplicity (hover for it), or an editable Quantity field (placeholder 1). Empty for the root. |
| Unit Value | Editable own value for leaves; Σ parts for parents with valued parts. Disabled when the value comes from Cost entities. Hover shows the source. |
| Basis | Estimated, Calculated, Measured for leaves with a value; Roll-up for parents. |
| Cont. | Contingency %. |
| CBE | Unit Value × Count, or the sum of parts. |
| Contingency | Contingency amount. |
| CBE + Cont. | Total. |
| Allocation | Editable allocation for the line (all instances). |
| Margin / Margin % | Allocation − total. |
| (flag) | ✓, ▲ Low (Margin below the required N%) or ✕ Over (CBE + contingency exceeds the allocation). |
A note under the table restates the rules. Collapsed branches are remembered.
Export XLSX
Writes <root> <quantity> Budget.xlsx with one sheet and a frozen header row. Its columns are Item (indented), Number, Count, Count Source, Unit Value, Basis, Contingency %, CBE (<unit>), Contingency, CBE + Contingency, Allocation, Margin, Margin % and Status.
The Status cell is coloured: Over allocation red, Below required margin yellow, OK green.
TPMs tab
List
The list shows Measures with the TPM label, then the requirements with a Threshold Value (in a SysML v2 project: the requirements with a known threshold). Select Show All Measures to list every Measure; the note beside it counts the measures and the requirements with a threshold.
The table shows Measure or Requirement, Current Estimate, Threshold, Objective, Planned Today and Status. Click a row to show its detail below.
Detail card
- Heading: the Measure (link), its status chip and the status message.
- Current Estimate (placeholder e.g. 11.8 kg), Threshold, Objective, Better when (higher or lower).
- Take Snapshot and + Milestone.
- The chart: Current estimate, Planned profile, Threshold, Objective, Breach region and a line for today. Point at a point for its value, date and note.
- Planned Profile: Milestone, Date, Planned Value, each editable, and × (Remove milestone).
- Estimate History (newest first): Date, Value, Source (Automatic or Snapshot), editable Note, × (Remove point).
Export XLSX
Writes TPM Report.xlsx with three sheets:
- Status: Number, Name, Current Estimate, Threshold, Objective, Planned Today, Status (with colour), Detail.
- Planned Profile: Measure, Milestone, Date, Planned Value.
- History: Measure, Date, Value, Source, Note.
Shortcuts
| Key | Action |
|---|---|
| ⌘Z / Ctrl+Z / ⇧⌘Z / Ctrl+Shift+Z | Undo or redo any value, basis, allocation, setting, milestone or snapshot change |
The tab is part of the page address: budgets opens Budget, budgets/tpm opens TPMs.
Messages
| Message | Meaning and fix |
|---|---|
| No root asset is selected. Use Select Root Asset… to choose the system to budget. | Pick a root. |
| No item under <root> has a value for "<quantity>". Enter values in the Unit Value column, or add a "<quantity>" attribute or Characteristic to the parts. | Nothing to roll up yet. |
| Unknown unit "<unit>". Enter a unit such as kg, W or $. | The display unit is not recognised. |
| "<text>" is not a number with units. Enter a value such as 12 kg. | An allocation, milestone or estimate could not be read. |
| "<value>" is not a number with units. (⚠) | A line's own value could not be read. |
| <kind> value in a <kind> budget. Fix the units. (⚠) | A value of another kind, left out of the sum. |
| The allocation is <kind>; the budget is <kind>. (⚠) | The allocation has the wrong kind of unit. |
| Own value <x> is replaced by the sum of its parts. (⚠) | A parent has its own value and valued parts. |
| Child allocations total <x>, more than this allocation. (⚠) | Over-allocated children. |
| No Measure has the TPM label and no requirement has a Threshold Value. Add the TPM label to a Measure, or select Show All Measures. | No TPMs yet. |
| This project has no Measures. Create a Measure in the Database to track it, or give a requirement a Threshold Value. | No Measures at all. |
| No plan or history yet. Add milestones or take a snapshot. | Empty chart. |
| No current estimate to record. Enter one first. | Take Snapshot without an estimate. |
| Date is missing. Pick a date. | Add Milestone without a date. |
| Snapshot recorded | Take Snapshot succeeded. |
| <x> is below the threshold <y>. / … above the threshold … | Breach. |
| <x> is below the planned <y> for today. / … above the planned … | At risk. |
| Meets the threshold <y> and the plan. / Meets the threshold <y>. / No threshold set. | On track. |
Limits
- One budget root and quantity is shown at a time; switch the quantity to see another budget.
- Contingency is set per basis for the whole budget, not per line.
- A multiplicity range counts its upper bound.
- Values in currencies other than US dollars are not converted to dollars.
Related
- Guide: MBSE example: budgets and analysis in a CubeSat model, with mass and power margins and TPMs.
- Interfaces — data rates and capacity checks use the same units.
- Verification — verify the requirements a TPM tracks.
- Risks, Issues & Decisions — trade studies that use budget quantities as criteria.
- SysML diagrams — multiplicities on the BDD and parametric constraints.
- Help: Budgets & TPMs, Track Budgets and TPMs, Parametric Diagram, Block Definition Diagram, Radar Diagram, Model Checks.