Risk Register

Every Risk in one sortable table, rated on the project risk scale.

Where to find it

  • In the navigation rail: Risks, Issues & Decisions → Risk Register.

Main actions

  • Page header: Risk Scale…, Export ▾ (Excel, CSV), + Opportunity and + New Risk.
  • Opportunities: a risk whose Kind is Opportunity is an uncertain benefit rather than a threat; its consequence rates the size of the benefit. The Kind column marks them, and the filter shows threats or opportunities only.
  • Columns: ID, Risk, Status, Owner, Handling, probability, consequence and Level, residual probability, consequence and level, Need-by date, Mitigations (mitigated by), Requirements at Risk and Trigger. Burn-down beside a name opens that risk's burn-down chart.
  • Requirements at Risk is derived from the model, not entered: relate a risk to what causes it (caused by, for example the Battery), and the requirements that element, its parts or the actions it performs satisfy or trace from are listed, with the path. Measures that specify the risk are listed in the Trace section of its inspector, and a requirement's Trace section lists the risks that reach it, highest level first.
  • Sort by any column; filter by level chips, status, handling or text. Status, Owner and Handling read as text: click one (or press Enter or F2 on it) to change it in place. Handling is the risk's Mitigation Status (LML 2.0), or its Handling Strategy in projects created before it.
  • Click a row to see the risk in the inspector (Esc deselects).

Tips

  • Each level shows its matrix cell, for example High (4×4); point at it for the percentages behind the cell.
  • Columns that are empty for every risk are hidden on screen; exports always include every column plus Exposure, Closure Rationale and Labels.